Labor Productivity Dashboard

Analysis for Labor Cost Code: LAB-BLK-002 (Blockwork)

Overall Productivity
92.5%

18.5 sqm/day vs 20 sqm/day target

Forecast
₦1,850,000

5.7% over budget

Corrective Actions
  • Material procurement improved
  • Weather-based scheduling
Next Month's Target

20+ sqm/day

Weekly Productivity Trend
Actual vs. Budgeted output per gang.
AI Root Cause Analysis

Productivity Drop (Week 3)

AI analysis correlates the 20% productivity drop with a 2-day delay in block delivery recorded in the material management module. The system suggests that the material request was made only 1 day before the required date, against a recommended 3-day lead time for this supplier.

Recommendation

Enable automated procurement alerts to notify the site manager when material requests fall within the supplier's average lead time. This can prevent future delays.

Budget vs. Actuals
Financial tracking for labor cost code LAB-BLK-002.
Original Budget₦1,750,000
Committed₦400,000
Actual to Date₦650,000
Remaining Budget₦700,000
Forecast at Completion₦1,850,000
Variance-₦100,000